Construction Updates

BBE renderingThe Blue Bell Elementary construction project, which began June 2023, will provide much needed classroom space, a new multi-purpose room and updated facilities to accommodate our growing enrollment. The most recent project updates are linked below along with the School Board meeting and Community Conversation presentations. 

 

BBE Phasing Plan 

PHASE 1    October 2023 – December 2023 - Complete

  • Bus lot Expansion

PHASE 2    October 2023 – December 2024 - In Progress

  • Construction of new addition
  • Create new parking area
  • Create new bus loop

PHASE 2B    June 2024 – August 2024

  • Renovation of existing classroom to allow existing corridor to tie into addition

PHASE 3    June 2024 – August 2024

  • Modify and expand existing front parking lot and parent drop off loop

PHASE 4   December 2024 – June 2025

  • Renovate existing kitchen, cafeteria and stage, converting areas to primarily Special Education classrooms and office space

Meeting Presentations 

April 24, 2024: Facilities Committee Update

February 5, 2024 Board of Directors Project Update

May 22, 2023 Blue Bell Construction Community Update

March 27, 2023 - Board of Directors Project Update 

May 3, 2022 - Blue Bell Elementary Community Meeting #3

April 19, 2022 - Facilities Committee Meeting

March 16, 2022 - Community Conversation #2 with Blue Bell Elementary 

January 5, 2022 - Community Conversation with Blue Bell Elementary 

December 12, 2022 - Act 34 Public Hearing

Construction Project Documents


View Phasing Plan PDF
View Classroom Diagram PDF

Phasing Diagram

Classroom diagram