Construction Updates
The Blue Bell Elementary construction project, which began June 2023, will provide much needed classroom space, a new multi-purpose room and updated facilities to accommodate our growing enrollment. The most recent project updates are linked below along with the School Board meeting and Community Conversation presentations.
BBE Phasing Plan
PHASE 1 October 2023 – December 2023 - Complete
- Bus lot Expansion
PHASE 2 October 2023 – December 2024 - In Progress
- Construction of new addition
- Create new parking area
- Create new bus loop
PHASE 2B June 2024 – August 2024
- Renovation of existing classroom to allow existing corridor to tie into addition
PHASE 3 June 2024 – August 2024
- Modify and expand existing front parking lot and parent drop off loop
PHASE 4 December 2024 – June 2025
- Renovate existing kitchen, cafeteria and stage, converting areas to primarily Special Education classrooms and office space
Meeting Presentations
April 24, 2024: Facilities Committee Update
February 5, 2024 Board of Directors Project Update
May 22, 2023 Blue Bell Construction Community Update
March 27, 2023 - Board of Directors Project Update
May 3, 2022 - Blue Bell Elementary Community Meeting #3
- Blue Bell Expansion Options Presentation
- Community Conversation #3 Slides
- Watch Community Conversation #3: Zoom Recording
April 19, 2022 - Facilities Committee Meeting
March 16, 2022 - Community Conversation #2 with Blue Bell Elementary
January 5, 2022 - Community Conversation with Blue Bell Elementary
December 12, 2022 - Act 34 Public Hearing